Compute the early, late, and slack times for the activities in the network that follows, assuming… 1 answer below »

Compute the early, late, and slack times for the activities in the network that follows, assuming a time-constrained network. Which activities are critical? What is the time constrained project duration?
Assume you are a computer using a software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!
Minimum slack
Smallest duration
Lowest identification number
Keep a log of each activity change and update you make each period-e.g., period 0-1,l-2, 2-3, etc. The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember to maintain the technical dependencies of the network.)
List the order in which you scheduled the activities of the project. Which activities of your schedule are now critical?
Recompute your slack for each activity given your new schedule. What is the slack for activity l? 4? 5?