Old Pueblo Engineering Contractors creates six-month “rolling” schedules, which are recomputed month 1 answer below »

Old Pueblo Engineering Contractors creates six-month “rolling” schedules, which are recomputed monthly. For competitive reasons (they would need to divulge proprietary design criteria, methods, and so on), Old Pueblo does not subcontract. Therefore, its only options to meet customer requirements are (1) work on regular time; (2) work on overtime, which is limited to 30 percent of regular time; (3) do customers’ work early, which would cost an additional $5 per hour per month; and (4) perform customers’ work late, which would cost an additional $10 per hour per month penalty, as provided by their contract.
    Old Pueblo has 25 engineers on its staff at an hourly rate of $30. The overtime rate is $45. Customers’ hourly requirements for the six months from January to June are JANUARY FEBRUARY MARCH APRIL MAY JUNE 5,040 4,040 6,040 6,040 4,840 4,000
Develop an aggregate plan. Assume 20 working days in each month. (Hint: Assume no backordered work at the end of the plan.) (Input all values as positive values. Leave no cells blank – be certain to enter “0” wherever required.)          January          February          March           April           May           June   Forecast work hours 5,040 4,040 6,040 6,040 4,840 4,000      Beginning inventory (work done earlier)      Work hours required      Regular work hours available      Overtime hours      Total planned hours      Ending inventory (early work completed)      Ending backorders (work to be done later)             January           February           March            April            May           June   Straight time $ $ $ $ $ $      Overtime      Inventory      Backorder         Total $ $ $ $ $ $          $